Skip Navigation
Home    West Albany High School Bond Project

West Albany High School Bond Project

West Albany High School is nearly seventy years old. The construction bond will be used in the development of an auxiliary gym, CTE spaces, student commons, and an auditorium, which will be available for use by the entire district.

Photos

Current Activities

Gerding Builders, LLC (GB) has established the site and begun preliminary reroute of existing underground utilities that were in the building’s path. LS Networks and GAPS fiber optic lines have been successfully crossed over and are now in the permanent location. Micro-piles have been installed on the west end of the gymnasium in preparation of support of the new structure and the Stadium area has been cleared and selectively demolished. Tennis courts have the base installed and will be scheduled for testing early the coming month. New construction of the Site Fire Access Road continues and will provide an access through the site for equipment and material deliveries.

Construction Schedule

SCHEDULE & KEY MILESTONES START COMPLETION % CPL
Pre-Design & Schematics

05/22/17

10/20/17 100%
Master Planning 08/22/17 11/20/17 100%
Design Development

01/15/17

04/30/18 100%
Construction Documents

04/30/18

12/21/18 100%
CM/GC Selection and Award 08/29/18 11/15/18 100%
Bid and GMP Acceptance

01/07/19

02/25/19 100%
Construction 03/01/19 06/15/20 9.4%
Building Commissioning 05/05/20 05/19/20 0%
Owner Occupancy 06/01/20 06/30/20 0%
Post Occupancy Evaluation 06/01/20 07/30/20 0%

Initial Design Drawings and Renderings

Click HERE for the initial design drawings.

Click HERE for photo-realistic design renderings.