West Albany High School Bond Project

West Albany High School is nearly seventy years old. The construction bond will be used in the development of an auxiliary gym, CTE spac-es, student commons, and an auditorium, which will be available for use by the entire district.

Photos

Current Activities

Gerding Builders, LLC (GB) has mobilized the site and established security fencing and the administrative staging area. GB has developed a well-organized and detailed construction schedule. The schedule is designed in a critical path management format and highlights the focus of primary quality control and commissioning activities. These activities are sequenced to track with the progress of the construction schedule.

Site activities performed this period include the establishment of temporary parking area with additional gravel, and delineation of faculty designated parking locations. Temporary facilities and security implements have been established, accompanied by environmental protective measurements.

New construction of the Site Fire Access Road has begun and will provide an access through the site for equipment and material deliveries. The installation of power conduits and new tennis courts preparatory ground work is also in progress.

Construction Schedule

SCHEDULE & KEY MILESTONES START COMPLETION % CPL
Pre-Design & Schematics

05/22/17

10/20/17 100%
Master Planning 08/22/17 11/20/17 100%
Design Development

01/15/17

04/30/18 100%
Construction Documents

04/30/18

12/21/18 100%
CM/GC Selection and Award 08/29/18 11/15/18 100%
Bid and GMP Acceptance

01/07/19

02/25/19 100%
Construction 03/01/19 06/15/20 6.7%
Building Commissioning 05/05/20 05/19/20 0%
Owner Occupancy 06/01/20 06/30/20 0%
Post Occupancy Evaluation 06/01/20 07/30/20 0%