Skip Navigation
Home    West Albany High School Bond Project

West Albany High School Bond Project

West Albany High School is nearly seventy years old. The construction bond will be used in the development of an auxiliary gym, CTE spaces, student commons, and an auditorium, which will be available for use by the entire district.

Photos

Current Activities

Gerding Builders, LLC (GB) has installed the auxiliary gym micro-piles and foundation. Existing tennis courts have been demolished and removed from site. Theater grades have been established and base of crushed rock is currently being placed. The stadium building has been selectively demolished and is now in the process of being reassembled to accommodate the new design. Four storage containers have been placed and are being prepared for painting. The new tennis court area is to grade and awaiting clear weather to continue asphalt installation. The Primary fire lane is near completion along with the drainage detention basin.

Construction Schedule

SCHEDULE & KEY MILESTONES START COMPLETION % CPL
Pre-Design & Schematics

05/22/17

10/20/17 100%
Master Planning 08/22/17 11/20/17 100%
Design Development

01/15/17

04/30/18 100%
Construction Documents

04/30/18

12/21/18 100%
CM/GC Selection and Award 08/29/18 11/15/18 100%
Bid and GMP Acceptance

01/07/19

02/25/19 100%
Construction 03/01/19 06/15/20 15.2%
Building Commissioning 05/05/20 05/19/20 0%
Owner Occupancy 06/01/20 06/30/20 0%
Post Occupancy Evaluation 06/01/20 07/30/20 0%

Initial Design Drawings and Renderings

Click HERE for the initial design drawings.

Click HERE for photo-realistic design renderings.