Skip Navigation
Home    West Albany High School Bond Project

West Albany High School Bond Project

West Albany High School is nearly seventy years old. The construction bond will be used in the development of an auxiliary gym, CTE spaces, student commons, and an auditorium, which will be available for use by the entire district.

Photos

Current Activities

Gerding Builders, LLC (GB) has cast the Auxiliary Gymnasium slab and is currently installing tilt panel formwork. The foundation footings in the Theater area are near complete. Selective demolition of the existing gymnasium and F-Wing have been completed in preparation of continuing the building through the new facilities. GB is near complete with the stadium renovation and is currently installing fixtures and ceiling grid.

The City of Albany is devising a mitigation plan to divert the flooding of the drainage system currently infiltrating the storm detention system. Current efforts are to divert waters upstream, to allow for the tennis court area to drain and achieve compaction.

Construction Schedule

SCHEDULE & KEY MILESTONES START COMPLETION % CPL
Pre-Design & Schematics

05/22/17

10/20/17 100%
Master Planning 08/22/17 11/20/17 100%
Design Development

01/15/17

04/30/18 100%
Construction Documents

04/30/18

12/21/18 100%
CM/GC Selection and Award 08/29/18 11/15/18 100%
Bid and GMP Acceptance

01/07/19

02/25/19 100%
Construction 03/01/19 06/15/20 25.5%
Building Commissioning 05/05/20 05/19/20 0%
Owner Occupancy 06/01/20 06/30/20 0%
Post Occupancy Evaluation 06/01/20 07/30/20 0%

Initial Design Drawings and Renderings

Click HERE for the initial design drawings.

Click HERE for photo-realistic design renderings.