Skip Navigation
Home    Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades are projects that will improve safety, security, and extend the life of the building. Projects are planned for every school in the district and include repairs or replacement of roofs, HVAC systems, plumbing, and flooring. There are also mechanical and technology upgrades occurring in many schools, as well as restroom modernization. All bond-funded projects are scheduled for completion by December 2021.

Technology Bond Project Overview, Click HERE.

See the project list for each school:

Elementary Schools
Middle Schools
High Schools


Elementary Schools

Central Elementary 

ADA Elevator - July

ADA Elevator, July

PROJECT DESCRIPTION
Installation of an elevator for ADA access to all 3 floors. Design and replacement of the old fire alarm systems with new digital fire alarm panels and devices.

CURRENT ACTIVITIES
Elevator: Elevator power issue was resolved. The elevator is back in service and functioning correctly. Contractor is currently working on completing final closeout documents for review. Final operation and maintenance manuals reviewed and accepted. Fire Alarm: Awaiting October to bid the project schools. We are sending out advance emails to build interest in the projects.

Fairmount Elementary

PROJECT DESCRIPTION
Roofing restoration or replacement

CURRENT ACTIVITIES
Roofing and metal trim complete. Final inspection to follow.

Lafayette Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA, Remodel Cafeteria, Mechanical Replacement and Domestic Water Lines.

CURRENT ACTIVITIES
Project COMPLETE.

Liberty Elementary

PROJECT DESCRIPTION
Construction of a parent loop, additional parking spaces and sidewalks, along with repaving the old lot and sidewalks. Roofing replacement.

CURRENT ACTIVITIES
This month construction finished up, and students returned to school utilizing the new parking lot and parent drop off loop. The work that occurred this month included finishing of the drainage swale, storm drain line, and landscaping. Punchlist items were also fixed by the contractor, including but not limited to patching damaged curbs and sidewalks. Roofing: Design reviews with GAPS Facilities. Bid document production. 

North Albany Elementary

PROJECT DESCRIPTION
Full replacement of fire alarm system.

CURRENT ACTIVITIES
Project COMPLETE.

Oak Grove Elementary

Oak Grove has it’s own web page HERE.

Oak Elementary

PROJECT DESCRIPTION
Roofing restoration or replacement

CURRENT ACTIVITIES
Design reviews with GAPS Facilities. Bid document production. Defining the sections of each school roof that will receive restoration or complete reroofing.

Periwinkle Elementary

PROJECT DESCRIPTION
Replace (19) Trane units (2) 1-1/2 Ton, (7) 3 Ton, (3) 4 Ton, (3) 5 Ton, (4) 7-1/2 Ton) and (1) makeup air unit with new package rooftop units. Mixing boxes and duct work for heating two classrooms with one RTU. Restroom modernization. Roofing.

CURRENT ACTIVITIES
Restrooms: Noted corrections needed from the punch list are being completed including refinishing the remodeled restroom floors. Final change order requests being negotiated. Roofing: Roofing and metal trim complete. Final inspection to follow.

South Shore Elementary

PROJECT DESCRIPTION
Paving and concrete upgrades throughout the District. Replacement, Coatings, New areas, Striping. Roofing restoration or replacement

CURRENT ACTIVITIES
Paving: COMPLETE. Roofing: Design reviews with GAPS Facilities. Bid document production. Defining the sections of each school roof that will receive restoration or complete reroofing.

Sunrise Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA and Replace Old Drinking Water Pipes. Roofing. 

CURRENT ACTIVITIES
Restroom: COMPLETE. Roofing: Roofing and metal trim complete. Final inspection to follow.

Takena Elementary

PROJECT DESCRIPTION
Roofing restoration or replacement

CURRENT ACTIVITIES
Design reviews with GAPS Facilities. Bid document production. Defining the sections of each school roof that will receive restoration or complete reroofing.

Tangent Elementary

PROJECT DESCRIPTION
Roofing restoration or replacement. Restroom Remodel.

CURRENT ACTIVITIES
Restrooms: Punchlist items being completed. Final change order requests being negotiated. Roofing: Roofing and metal trim complete. Final inspection to follow.

Timber Ridge

PROJECT DESCRIPTION
The project includes the modification of two Computer Labs on the first floor into Food Science lab and Paxton Patterson lab. A concrete slab outside of the Maker Lab will also be added. Two bond premium alternates are included in the project, renovation of the existing Computer Lab on the second floor into a Classroom and an adjacent Classroom will be renovated to a Science Lab.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Waverly Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA Compliance and Replace Domestic Drinking Water Pipes. Design and replacement of the old fire alarm systems with new digital fire alarm panels and devices. Roofing replacement

CURRENT ACTIVITIES
Restrooms: Temporary student restroom doors replaced with the correct version. Punchlist items being corrected. Final change order requests being negotiated. Fire Alarm: Awaiting October to bid the project schools. We are sending out advance emails to build interest in the projects. Roofing: Design reviews with GAPS Facilities. Bid document production. 


Middle Schools

Calapooia Middle 

PROJECT DESCRIPTION
Renovation of five spaces to include Woodshop, Maker Lab, Digital Lab, Classroom 15 and Food Science. Renovation of library to connect with an Applied Learning space is shown as a Bond Premium Additive Alternate as well as renovation work to the Clothing Lab. Misc. CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Memorial Middle 

PROJECT DESCRIPTION
Modification of the existing Science Classroom, Leadership Classroom, Food Science & Communications Classroom into a new Science Lab, Fabrication Lab, Maker Space, and Digital Lab; CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, roof replacement and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
All the rooms are finished and occupied. We are currently in the process of negotiating the final change orders and finishing up the commissioning of the new classrooms.

Initial Design Drawings HERE.

North Albany Middle

PROJECT DESCRIPTION
Modify existing Art Classroom, Four Classrooms into CTE Labs and Classroom; Critical Facility Upgrades.

CURRENT ACTIVITIES
Our current activities include framing of walls and finishing of Mechanical, Electrical, Plumbing (MEP), infilling concrete, installing the new window systems and shared walls in all the new spaces.


High Schools

South Albany High 

South Albany High School has it’s own bond page HERE.

West Albany High

West Albany High School has it’s own bond page HERE.