Skip Navigation
Home    Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades are projects that will improve safety, security, and extend the life of the building. Projects are planned for every school in the district and include repairs or replacement of roofs, HVAC systems, plumbing, and flooring. There are also mechanical and technology upgrades occurring in many schools, as well as restroom modernization. All bond-funded projects are scheduled for completion by December 2021.

Technology Bond Project Overview, Click HERE.

See the project list for each school:

Elementary Schools
Middle Schools
High Schools


Elementary Schools

Central Elementary 

PROJECT DESCRIPTION
Installation of an elevator for ADA access to all 3 floors.

CURRENT ACTIVITIES
Site visits by the Contractor, Andy Medcalf Construction Company (AMCC) and subcontractors in preparation for construction. Planning and layout of construction along with completing submittals.

Lafayette Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA, Remodel Cafeteria, Mechanical Replacement and Domestic Water Lines.

CURRENT ACTIVITIES
Project COMPLETE.

Liberty Elementary

PROJECT DESCRIPTION
Construction of a parent loop, additional parking spaces and sidewalks, along with repaving the old lot and sidewalks.

CURRENT ACTIVITIES
This month we held our preconstruction meeting with the Contractor, RiverBend Construction, our design consultants and the landscaping contractor. We discussed plans for the start of construction, as well as laying out expectations for correspondence and documentation. Submittals are in the process of review for the landscaping and paving by Civil West and Dougherty Landscape Architects.

North Albany Elementary

PROJECT DESCRIPTION
Full replacement of fire alarm system.

CURRENT ACTIVITIES
Project COMPLETE.

Oak Grove Elementary

Oak Grove has it’s own web page HERE.

Oak Elementary

Periwinkle Elementary

PROJECT DESCRIPTION
Replace (19) Trane units (2) 1-1/2 Ton, (7) 3 Ton, (3) 4 Ton, (3) 5 Ton, (4) 7-1/2 Ton) and (1) makeup air unit with new package rooftop units. Mixing boxes and duct work for heating two classrooms with one RTU. Restroom modernization. Roofing.

CURRENT ACTIVITIES
New metal trim colors being approved. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period.

South Shore Elementary

PROJECT DESCRIPTION
Paving and concrete upgrades throughout the District. Replacement, Coatings, New areas, Striping.

CURRENT ACTIVITIES
Project COMPLETE.

Sunrise Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA and Replace Old Drinking Water Pipes. Roofing. 

CURRENT ACTIVITIES
Restroom COMPLETE. New metal trim colors being approved for roof. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period. 

Takena Elementary

Tangent Elementary

PROJECT DESCRIPTION
Roofing restoration or replacement. Restroom Remodel.

CURRENT ACTIVITIES
New metal trim colors being approved. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period.

Timber Ridge

PROJECT DESCRIPTION
The project includes the modification of two Computer Labs on the first floor into Food Science lab and Paxton Patterson lab. A concrete slab outside of the Maker Lab will also be added. Two bond premium alternates are included in the project, renovation of the existing Computer Lab on the second floor into a Classroom and an adjacent Classroom will be renovated to a Science Lab.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Waverly Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA Compliance and Replace Domestic Drinking Water Pipes.

CURRENT ACTIVITIES
Weekly site visits with the contractor and subcontractors for layout and preparation. Each Wednesday we are taking advantage of student early release. It is a great time for contractor visits, assisting them to be ready for the actual construction period. Product submittals being reviewed.


Middle Schools

Calapooia Middle 

PROJECT DESCRIPTION
Renovation of five spaces to include Woodshop, Maker Lab, Digital Lab, Classroom 15 and Food Science. Renovation of library to connect with an Applied Learning space is shown as a Bond Premium Additive Alternate as well as renovation work to the Clothing Lab. Misc. CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Memorial Middle 

PROJECT DESCRIPTION
Modification of the existing Science Classroom, Leadership Classroom, Food Science & Communications Classroom into a new Science Lab, Fabrication Lab, Maker Space, and Digital Lab; CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, roof replacement and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
With the summer construction period approaching, we are ramping up our project meetings and scheduling our consultants for key dates. The General Contractor, Andy Medcalf Construction Company (AMCC) and their sub-contractors are beginning to order and take delivery of the material they will need for the project.

Initial Design Drawings HERE.

North Albany Middle

PROJECT DESCRIPTION
Modify existing Art Classroom, Four Classrooms into CTE Labs and Classroom; Critical Facility Upgrades.

CURRENT ACTIVITIES
HMK has been working diligently to ensure each and every submittal is checked against the project documents and GAPS District Standards.


High Schools

Albany Options School

South Albany High 

South Albany High School has it’s own bond page HERE.

West Albany High

West Albany High School has it’s own bond page HERE.