Skip Navigation
Home    Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades at Existing Schools

Critical Facility Upgrades are projects that will improve safety and security or extend the life of the building. Projects are planned for every school in the district and include repairs or replacement of roofs, HVAC systems, and flooring. All bond-funded projects are scheduled for completion by December 2021.

Technology Bond Project Overview, Click HERE.

See the project list for each school:

Elementary Schools
Middle Schools
High Schools


Elementary Schools

Central Elementary 

PROJECT DESCRIPTION
Installation of an elevator for ADA access to all 3 floors.

CURRENT ACTIVITIES
Bids were received on December 12, 2018, we received 2 bids. One from Andy Medcalf Construction and one from First Cascade Corporation. Bids are being evaluated for a recommendation to the School Board at the January 28th board meeting.

Lafayette Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA, Remodel Cafeteria, Mechanical Replacement and Domestic Water Lines.

CURRENT ACTIVITIES
Project COMPLETE.

Liberty Elementary

PROJECT DESCRIPTION
Construction of a parent loop, additional parking spaces and sidewalks, along with repaving the old lot and sidewalks.

CURRENT ACTIVITIES
The bidding period closed; RiverBend Materials was the low bid of the four bidders. The bid was presented for the School Board’s approval at the April 22, 2019 meeting, the Board awarded the contract. Quotes for special testing and inspections are being requested.

North Albany Elementary

PROJECT DESCRIPTION
Full replacement of fire alarm system.

CURRENT ACTIVITIES
Project COMPLETE.

Oak Grove Elementary School

Oak Grove has it’s own web page HERE.

Oak Elementary School

Periwinkle Elementary

PROJECT DESCRIPTION
Replace (19) Trane units (2) 1-1/2 Ton, (7) 3 Ton, (3) 4 Ton, (3) 5 Ton, (4) 7-1/2 Ton) and (1) makeup air unit with new package rooftop units. Mixing boxes and duct work for heating two classrooms with one RTU.

CURRENT ACTIVITIES
New metal trim colors being approved. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period.

South Shore Elementary School

PROJECT DESCRIPTION
Paving and concrete upgrades throughout the District. Replacement, Coatings, New areas, Striping.

CURRENT ACTIVITIES
Project COMPLETE.

Sunrise Elementary

PROJECT DESCRIPTION
Remodel Restrooms for ADA and Replace Old Drinking Water Pipes. Roofing. 

CURRENT ACTIVITIES
Restroom COMPLETE. New metal trim colors being approved for roof. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period. 

Takena Elementary School

Tangent Elementary School

PROJECT DESCRIPTION
Roofing restoration or replacement. Restroom Remodel.

CURRENT ACTIVITIES
New metal trim colors being approved. Final staging plans approved. All submittals approved. All pea gravel was removed from the project roofs during Spring Break. It provides a head start for the Summer construction period.

Timber Ridge School

PROJECT DESCRIPTION
The project includes the modification of two Computer Labs on the first floor into Food Science lab and Paxton Patterson lab. A concrete slab outside of the Maker Lab will also be added. Two bond premium alternates are included in the project, renovation of the existing Computer Lab on the second floor into a Classroom and an adjacent Classroom will be renovated to a Science Lab.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Waverly Elementary School

PROJECT DESCRIPTION
Remodel Restrooms for ADA Compliance and Replace Domestic Drinking Water Pipes.

CURRENT ACTIVITIES
Weekly site visits with the contractor and subcontractors for layout and preparation. Each Wednesday we are taking advantage of student early release. It is a great time for contractor visits, assisting them to be ready for the actual construction period. Product submittals being reviewed.


Middle Schools

Calapooia Middle 

PROJECT DESCRIPTION
Renovation of five spaces to include Woodshop, Maker Lab, Digital Lab, Classroom 15 and Food Science. Renovation of library to connect with an Applied Learning space is shown as a Bond Premium Additive Alternate as well as renovation work to the Clothing Lab. Misc. CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
Project COMPLETE.

Initial Design Drawings HERE.

Memorial Middle 

PROJECT DESCRIPTION
Modification of the existing Science Classroom, Leadership Classroom, Food Science & Communications Classroom into a new Science Lab, Fabrication Lab, Maker Space, and Digital Lab; CFU projects include seismic upgrades, Locker Room and Restroom Updates, Food Science upgrades, roof replacement and replacing plumbing fixtures and piping.

CURRENT ACTIVITIES
We are now over half way through the submittal approval process. Each product that the contractor wishes to use on the project has to be reviewed by the Design Team to ensure that it meets all the requirements of the project.

Initial Design Drawings HERE.

North Albany Middle

PROJECT DESCRIPTION
Modify existing Art Classroom, Four Classrooms into CTE Labs and Classroom; Critical Facility Upgrades.

CURRENT ACTIVITIES
Coordinating the many subcontractors that are going to be working on this project to get the administration portion behind us. This is so we can focus on getting the project complete without any surprises later on.


High Schools

Albany Options School

South Albany High 

South Albany High School has it’s own bond page HERE.

West Albany High

West Albany High School has it’s own bond page HERE.